Projects  |  Erco Worldwide

Coquitlam City Centre Pump Station & Forcemain

PROCESS CHEMICAL PLANT

RME Logo

General Contractor
Ross Morrison Electrical

Engineering
ANDRITZ Automation

Location
100 Forester St North Vancouver B.C V7H 1W4

Capital Value of Project
$200,000

Year of Project
2013

Industry
Process chemical plant

OVERVIEW

Ross Morrison Electrical was contracted by Erco Worldwide to decommission and remove there existing main PCB filled bulk oil circuit breaker replacing it with a new 69KV SF6 Breaker. This project also included the supply and installation of new protection and control panels and the installation of a new 69KV Alstom Motor Operated Disconnect Switch.