Projects  |  Metro Vancouver

Annacis Island WWTP 64KV Substation Protection and Controls Upgrade Project

Water and Wastewater

RME Logo

General Contractor
Ross Morrison Electrical

Engineering
ABV

Location
1299 Derwent Way, Delta B.C V3M 5V9

Capital Value of Project
$1,000,000

Year of Project
2019-2020

Industry
Water and Wastewater

OVERVIEW

The Annacis Island wastewater treatment plant treats about 175 billion litres of wastewater every year. Located in Delta at 1299 Derwent Way, the plant provides secondary treatment to wastewater for over 1 million residents in 14 municipalities. In 2019 Ross Morrison was contracted to manufacture and replace five (5) existing circuit breaker control panels in the plants 64KV substation Control Building. This project certainly stands out for us as 25years ago Ross Morrison built this substation including these existing P&C panels.