Ross Morrison completed the electrical installation which included pulling 7 KM of 5KV cable in underground duct from the powerhouse to the Intake. 108- 15KV Terminations (5KV / 12.5KV)
General Contractor
Andritz Hydro
Engineering
ANDRITZ HYDRO Canada Inc
Location
60KM NW of Pemberton B.C.
Capital Value of Project
$300,000,000
Year of Project
2014-2016
Industry
Energy and Utilities